JNNURM is a Central government scheme which is implemented by the In the report, CAG stated that the ministries of the Central government were not. The CAG in its report on “Performance Audit of JNNURMā€, tabled in Parliament on Thursday, said though two-year time was granted to complete each project. In the report, the CAG stated that the ministries of the central government were not equipped to monitor a project of JNNURM’s magnitude.

Author: Voodoogor Megore
Country: Netherlands
Language: English (Spanish)
Genre: Spiritual
Published (Last): 20 June 2015
Pages: 390
PDF File Size: 20.49 Mb
ePub File Size: 5.79 Mb
ISBN: 950-7-75493-426-1
Downloads: 90786
Price: Free* [*Free Regsitration Required]
Uploader: Vudotaxe

However, as on 31 Marchin respect of the housing projects, only 22 of the approved projects were completed,” the CAG report said. At a press conference earlier this week, housing and urban poverty alleviation minister, Kumari Selja, had stated that urban housing shortage in India has decreased from October 18, Out of the completed dwelling units, onlydwelling units were occupied. Related Topics Industry National housing and urban planning.

Only 22 of 1, housing projects completed under JNNURM: CAG – The Hindu

The report further rapped the Union ministries of urban development and housing and poverty alleviation for not being able to bring about reforms in the governance of urban local bodies ULBs.

Please Email the Editor. Against an allocation of 66, Only 11 out of sample projects selected by it for the period to had been completed and also referred to “various deficiencies” that it found in the implementation of these projects, the report stated.

AUDA spent Rs crore to build 7, units in six years,leaving under construction. In respect of urban infrastructure projects, we observed that out of the 1, projects approved, unnurm projects 18 per cent were completed,” the report stated.

  ASTM D6439 PDF

The remaining 73 housing projects were incomplete till March In the 56 selected sewerage projects, only four of the projects were complete. Printable version Dec 31, 9: CAG found that out of 39 mission cities selected for audit scrutiny, mechanism for collection of user charges for water supply and solid waste management was reportedly established in seven and five cities respectively.

One was innurm, while five projects were deferred.

JNNURM poorly implemented, affected with lack of unaccountability, unfinished projects: CAG report

At last, Corporation gets funds. The CAG report said that in some cases, there were deficiencies in selection of beneficiaries of houses for urban poor which led to risks of ineligible beneficiaries getting the benefit.

It also suggests that delays should be monitored and timely implementation of projects be given due importance. They do not represent the views or opinions of The Indian Express Group or its staff. In Uttar Pradesh, not a single urban infrastructure project had been completed in seven mission cities whereas in Delhi only four out of 28 sanctioned were completed. The report said that against an allocation of Rs 66, New Delhi, Fri Nov 30 The report, which was tabled in the Parliament today, also observed that a crucial objective of bringing about reforms in the governance of Urban Local Bodies ULBs could not be achieved through the scheme.

Only 22 housing projects for poor completed under JNNURM, says CAG

This,also despite AUDA not having signed a tripartite agreement with the state government and the Centre,a necessary condition for accessing Mission funds. None of cities, according to Union urban development ministry, jnnugm implemented property title registration system. In reforms Collection of user charges: Another gross irregularity on the part of the AMC is that it transferred to AUDA a housing project in ,for which it had got Rs 89 crore to build 8, units in Ahmedabad along with funds.

  CONCEPTOS AVANZADOS OMAHA LIMITE BOTE PDF

We also reserve the right not to publish repory that are abusive, obscene, inflammatory, derogatory or defamatory. Fill in your details: Comments are automatically posted live; however, indianexpress. Get instant notifications from Economic Times Allow Not now You can switch off notifications anytime using browser settings.

Only 22 housing projects for poor completed under JNNURM, says CAG

Funds diverted Only 11 out of sample projects selected by CAG for the period to were completed, the CAG report states. CAG report on demonetisation to be ready before Budget Session.

Delays were due to non availability of land, forest and environment clearance, clearance from SPCB, non clearance of the site and public agitation. For example, under BSUP, Kochi Phase 2 Jnnurmm houses in Kerala, beneficiaries of three colonies were corporation employees with regular source of income who onn not eligible for assistance admissible under the scheme of BSUP.